Sammamish’s Town Center is a major topic of debate in the upcoming city council election. Currently, developers are actively building and planning Town Center housing, amenities, and infrastructure.
According to the City’s draft Town Center Plan in which the city originally agreed to build 2,000 housing units, 326 units and 134,000 square feet of commercial space have already been built. The number of units was amended with a 6-1 vote of the City Council at the Tuesday, July 15 meeting from 2,000 to 4,000 units. Two distinct components of Town Center development totaling 730 housing units are presently in the works.
Matthew Samwick, the CEO of Innovation Realty Partners, indicated the first phase consists of three main parts. The first is a public open plaza, surrounded by commerce and connected by trail to Sammamish Commons. Samwick stated that amenities will be designed according to feedback from a public community survey, which has received over 1,200 responses. The second is a pair of residential buildings, Brownstones West and Brownstones East, with a total of 86 townhomes. The third and largest section is a set of two seven-story, mixed-use buildings.
“The project includes 156 apartments, 144 senior-restricted units, a parking garage, and 88,000 square feet of ground-floor commercial space,” said Angie Millar, the City’s communications director, in an email to the Sammamish Independent, regarding the third component of phase one.
According to Samwick, progress on Brownstone West and East, located at the intersection of Southeast 4th Street and 222nd Place Southeast, the second part of phase one, started in 2018. Brownstones West will open for sale in 2026, while construction on Brownstones East has not yet started. Samwick estimated that work on the mixed-use buildings will begin within two years and will take three years to complete.
“The idea that thousands of housing units will appear overnight, or in a short time period, is completely false,” said Samwick in an email to the Sammamish Independent.
The second phase is a 344-unit, seven-story apartment and mixed-use building. Millar stated that the plans for the second phase are still in review.
“The next step is for the developer to apply for building permits. This step can take over a year to complete once construction plans are drawn,” said Millar.
Developers are currently working with the city on further steps beyond the second phase. Some proposals include a senior living facility and connections to future transit. All development is capped at about 85 feet high or less, depending on the use of the structure.
“On April 1, 2025, City Council directed staff to no longer consider 150-foot building heights,” said Millar. While the issue was not determined by a vote, all seven city council members agreed in discussion that buildings that high were not suitable for Sammamish.
But building height is not the only concern for many in Sammamish. Residents also cite runoff and traffic congestion. The city is attempting to address a variety of development issues before they arise. According to Samwick, developers are required to pay tens of millions to support construction of new roads. New sections on SE 5 St., SE 6 St. and 224th St. are expected to be complete by spring 2026.
Millar stated that the city expects that Town Center will only increase traffic by seconds in critical intersections identified by the Transportation Master Plan thanks to new roads.
“We’ve heard concerns about traffic on 228th and Inglewood Hill Road. While current data doesn’t show major impacts there, we have projects underway—like the Sahalee Corridor Study and the proposed 2027 Centers and Corridor Plan—that will take a closer look at traffic on key roads, including 228th from Pine Lake to Inglewood,” said Millar.
However, some residents expressed skepticism that traffic will be truly diverted to new routes.
Melody Yang, a six-year resident of Sammamish in her 30s said in an interview with the Sammamish Independent, “228 is so popular I think many people will go there still instead of to new ones. So you might get a few thousand, a few hundred more cars clogging the main roads.”
Developers will also pay $5.2 million for a new regional stormwater vault, which is expected to finish before spring 2026. The vault is intended to store excess rainwater and prevent runoff.
The city’s 2023 hydrology study projects that total runoff will decrease in the Inglewood Town Center, the Thompson Town Center, the Middle Ebright Wetland, and the Ebright Creek Mouth regions, but increase in the George Davis Creek Mouth after Town Center construction. George Davis Creek Mouth opens into Lake Sammamish.
Overall, Samwick hopes the Town Center can be a vibrant common space for residents.
“The goal is to create a place that truly feels like the heart of Sammamish—where people can meet up, shop, relax, and enjoy public open spaces all in a walkable area,” said Samwick.
Matthew Samwick is the Chief Executive Officer of Innovation Realty Partners (IRP) and is the developer of the Town Center in Sammamish. IRP is also a sponsor of the Sammamish Independent.